High-Rise Delays in Hyderabad: Vasavi, Sahiti & Bhuvanteja Under TG-RERA Scanner

Handover delays are no longer theoretical in West Hyderabad multiple prominent high-rise developments are facing regulatory enforcement from the Telangana Real Estate Regulatory Authority (TG-RERA).



Here are key examples of delayed projects and the regulatory precedents set by TG-RERA:



• Vasavi Lake City (Hafeezpet): After repeated postponement of the August 2023 handover date, TG-RERA ordered Vasavi Realtors to pay homebuyers 10.8% p.a. delay interest until physical possession is delivered.


• Bhuvanteja Aara (Velimela): Promised for December 2023, the project stood at barely 20% completion by mid-2024. TG-RERA imposed cash penalties and ordered full refunds with 11% interest for impacted allottees.


• Sahiti Infratec (Gundlapochampally/Kollur): Severe construction stalls led TG-RERA to blacklist the builder, recommend criminal prosecution, and direct refund payouts across affected projects.


• 4-Month Blanket Relief: TG-RERA granted a 4-month extension for projects due after Feb 28, 2026, due to material supply chain bottlenecks meaning even active sites could push their target handovers into late 2026 or 2027.



Is your project currently facing physical construction slowdowns or extended possession dates in Hyderabad? Share the project name below to check its status!

16 Comments

Arjungaddamedi
Is there any construction update on Vasavi Atlantis in Narsingi as of mid-2026?
Kumar123

@Arjungaddamedi Vasavi Atlantis structural work on upper tower floors is ongoing. Work speed is relatively active compared to Lake City, though finishing stages are expected to extend into 2027.

Srinivasred78
Can individual buyers approach TG-RERA directly without hiring a high-fee real estate lawyer?
Kumar123

@Srinivasred78 Yes, the TG-RERA online portal allows individual allottees to file Form M or Form N directly by uploading the Agreement for Sale, payment receipts, and notice communications.

Waseemkhan
What rate of interest is TG-RERA currently granting on refund orders for delayed projects in West Hyderabad?
Kumar123

@Waseemkhan TG-RERA mandates interest at SBI MCLR + 2%, which currently equates to around 10.8% to 11.0% per annum calculated from the original committed possession date.

Neohyderabadprop
How does TG-RERA enforce refund orders if the developer's bank accounts are frozen or attached?
Kumar123

@Neohyderabadprop When developers fail to comply with refund orders, TG-RERA issues Revenue Recovery Certificates (RRC) to the District Collector to attach and auction the developer's land assets.

Devkumar123
How are buyers in Sahiti Sarovani handling bank EMI payments when construction has completely stopped?
Kumar123

@Devkumar123 Many buyers in Sahiti Sarovani filed joint petitions with TG-RERA and Debt Recovery Tribunals (DRT) seeking temporary suspension of pre-EMI demands from lenders under subvention schemes.

Anjalimathur
Are there any recent TG-RERA orders regarding delays in Bhuvanteja's projects in Bachupally or Kollur?
Kumar123

@Anjalimathur Yes, TG-RERA issued show-cause notices for multiple Bhuvanteja sites where civil work halted. Allottees are advised to file Section 18 refund applications jointly on the portal.

Pavanreddy
What is the status of Vasavi Ananda Nilayam in 100 Feet Road LB Nagar? Has TG-RERA issued any delay warnings for that project?
Kumar123

@Pavanreddy Vasavi Ananda Nilayam is currently progressing on structural work, but buyers have noted timeline revisions. While TG-RERA hasn't blacklisted it like Sahiti, homebuyers are tracking slab completion velocity closely.

RealtyHyd
Does the 4-month blanket extension apply automatically to all projects registered under TG-RERA, or do builders need to submit proof of supply chain disruption?
Kumar123

@RealtyHyd Developers must submit formal justification and revised milestone charts on the TG-RERA portal to claim the 4-month extension. It is not an unconditional waiver across the board.